My Thuan 2 Bridge project nearly 50% complete

By Trung Chanh

Must read

CAN THO – The project to build My Thuan 2 Bridge and roads leading to the bridge is 47.27% complete, exceeding the progress target by 1.83%, and a package of the project has been completed, according to the Project 7 Management Board under the Ministry of Transport.

The project has five packages–XL.01, XL.02, XL.03A, XL.03B and XL.04. Of which, the XL.01 package is 77.06% complete, meeting the progress target, while the XL.02, XL.03B and XL.04 packages are 65.64%, 1.9% and 80.31% complete, respectively, exceeding the targets.

The XL.03A package has been completed.

According to the Project 7 Management Board, nearly VND2.5 trillion has been disbursed for the project, or 99.2% of the total capital allocated for the project.

The project is connected to the Trung Luong-My Thuan and My Thuan-Can Tho expressways. The bridge will be some 1.9 kilometers long, while roads leading to the bridge will be over 4.7 kilometers long.

The project is part of the eastern North-South expressway project.