HCMC – Construction work at the An Phu intersection is being accelerated around the clock, with authorities aiming to open the underpass and overpasses before the Lunar New Year holiday in February 2026 and complete the entire project by June 30, 2026.


Overpass N3 has completed pillars T5 to T11 and abutment M2. Workers are now building foundations for pillars T1 to T3 and abutment M1, while preparing for a second concrete pour for the span between T5 and T6.
Overpass N4 has finished pillars T4 to T10 and abutment M2. Construction is underway on foundations for pillars T1 to T3, abutment M1, load-reducing piles, and retaining walls.