25 C
Ho Chi Minh City
Thursday, September 4, 2025

Long Thanh airport construction continues through National Day holiday to stay on schedule

Author:

By Le Vu
spot_img
HCMC – Nearly 14,000 engineers and workers are working through the National Day holiday at the Long Thanh International Airport construction site. Key components are being expedited to meet the completion target in December this year.

Covering 5,000 hectares and requiring a total of nearly VND336.63 trillion, Long Thanh International Airport is an infrastructure project of national importance. Once completed in three phases, the airport will have an annual capacity of 100 million passengers and five million tons of cargo.

Phase one, expected to begin operations in 2026, will serve 25 million passengers and 1.2 million tons of cargo annually.

According to Airports Corporation of Vietnam (ACV), the entire project is being executed under the “three shifts, four crews” model, with work carried out during holidays, Tet, and weekends. Around 14,000 engineers, workers, and 3,000 pieces of machinery have been mobilized, with hundreds of work fronts operating simultaneously across the site.
Phase one of the project comprises 11 contract packages, focusing on critical facilities such as the passenger terminal, internal road system, aircraft aprons, fuel supply system, and technical infrastructure.
Among them, package 5.10 – the construction of the passenger terminal – is considered the most important. A consortium of contractors responsible for this package has mobilized nearly 6,000 engineers, workers, and equipment, maintaining nonstop work through the holiday. From above, the lotus-shaped roof – the terminal’s architectural highlight – has begun to take shape.
The passenger terminal has so far completed the reinforced concrete structure for both the underground and four above-ground levels. Installation of steel frames, glass structures, and rough construction is largely finished.
Contractors are now focusing on flooring, ceilings, and interior cladding
In addition to the passenger terminal, other components such as access roads, runway No. 2, aircraft aprons, cargo terminal, fuel supply system, and technical infrastructure are also being accelerated, with thousands of workers and machines engaged
Key operational equipment for the terminal, including the baggage handling system (BHS), visual docking guidance system (VDGS), escalators, and stairways, has been delivered and is being installed
ACV said all components must be completed in 2025. Workers on duty during the holiday are paid wages and allowances in line with regulations. The investor has deployed supervisory teams around the clock to ensure safety and construction quality.
The Prime Minister has directed that the project be inaugurated on December 19 this year

Read More

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here