31.7 C
Ho Chi Minh City
Monday, December 23, 2024

Underpass in front of new Mien Dong Coach Station ready Wednesday

The Saigon Times

Must read

HCMC – An underpass in front of the new Mien Dong Coach Station will be opened to traffic on November 30, according to the HCMC Transportation Works Construction Investment Project Management Authority (TCIP).

Located along the Hanoi Highway, the underpass is 670 meters long and eight meters wide. It is an important component of the interchange project in front of the new Mien Dong Coach Station.

The underpass will help separate traffic flows and ease traffic congestion at the gateway of HCMC.

Work on the VND75-billion project commenced in March 2020 and was then expected for completion in December 2021. But construction delays pushed back the opening date of the underpass to the end of November this year.

The TCIP will continue to complete other components of the interchange project, including another underpass facilitating traffic from Dong Nai to HCMC, two overpasses, and a pedestrian bridge allowing passengers to walk from an elevated station of the city’s Metro Line No.1 to Mien Dong Bus Station.

The total cost of this interchange project is estimated at VND437 billion.

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest articles