HCMC cancels 169 long-delayed housing projects

By T.HUY

Must read

HCMC – Cracking the whip against delayed projects, HCMC canceled 169 out of 357 long-delayed housing projects.

At the eighth session of the 10th-tenure HCMC People’s Council, Nguyen Toan Thang, director of the Natural Resources and Environment Department, said that the department had joined hands with other departments to review 401 housing projects in the city, 87 of which are eligible to be licensed.

As for handling projects far behind schedule from 2016 to 2022, the council has come up with 13 resolutions permitting 1,532 projects for land use change and acquisition.

Until now, 451 projects were completed, and 718 are being implemented. Of these implementing projects, there are 357 projects behind schedule, 169 of which have been canceled and the rest are being considered.

Thang affirmed that the relevant agencies would drastically handle the projects lagging behind schedule without an acceptable reason.