Work on Bao Loc-Lien Khuong expy set to start by end-July

By Truc Dao

Must read

HCMC – The government of Lam Dong Province has directed agencies to finalize the list of affected parties and issue land acquisition notices by June 15, ensuring the Bao Loc-Lien Khuong Expressway project will begin construction by the end of July 2025.

On the afternoon of May 30, the Lam Dong People’s Committee held an online meeting with relevant units and localities to review the preparations for the groundbreaking of the expressway project.

The Lam Dong Province People’s Committee instructed relevant agencies and localities to compile a list and issue written land acquisition notices to affected organizations and individuals by June 15, aiming to start work on the expressway by the end of July 2025.

After the provincial government approves the investor selection results, the Lam Dong Transportation Project Management Board will work with the investor to conduct surveys and finalize the design documents for the selected section.

The board will then coordinate with the investor and relevant agencies to prepare the site for the groundbreaking ceremony.

By June 20, relevant localities must complete the land pricing documents for compensation and site clearance and submit them to the Department of Natural Resources and Environment for consolidation.